The Gas Delivery Interconnection Project Will Begin From Northeast to West Sichuan

Sinopec Southwest Oil and Gas Field Company is about to construct the Interconnection Project from Northeast to West Sichuan.

Such project is from its first station Puguang, by way of Pingchang and Yuanba—its division stations, to the terminal station Deyang, covering 6 cities and 13 counties, which is altogether 430 kilometer with 1016mm pipe diameter.

Besides, it is about 52 kilometer from Tong Jianghe bay to Pingchan division station, with 610mm pipe diameter, 10Mpa average press, incuding 19 tunnels, 2 station yards and 6 pipeline cut-off valves. This project plans to begin before August 30. Presently, it's in intense preparations.